Process Editing

Now that we have defined a resource, we must specify how and when that resource is used in the processing logic.

In the Phase 1 model we used only constant processing times. Now, due to variability associated with the operator, we must represent the loading and inspection times as distributions.

In the example below, CellOp loads the blank at mill NC_302L and is then FREEd to perform other operations. When the Blank has finished processing, the entity is moved with the CellOp to the degreasing machine.

Process Edit Table and corresponding operation logic

 

Routing Edit Table